This document provides an overview of how you can obtain capacity for each
consumption option in Cluster Director.
Cluster Director supports several
consumption options
to help you get and use compute resources.
How to obtain capacity
The following table describes how you can obtain capacity for each consumption
option.
Consumption option
Process for obtaining capacity
Pricing implications
Future reservations for more than 90 days (for capacity blocks)
To get future reservation resources, the process is as follows:
Contact your account team to
reserve capacity.
You can request compute instances and, optionally, a
Hyperdisk pool.
Google increases your quota, and then provisions your requested
resources at your specified start date and for your specified
duration.
When you
create a
cluster, select the Use reservation consumption
option and then specify your reservation. Cluster Director creates
the cluster from your reserved capacity.
You pay for the entire reservation period, whether you use the reserved
resources or not. For more information, see the pricing for
reservations and
Hyperdisk
pools.
Future reservations for up to 90 days (in calendar mode)
To get future reservation resources, the process is as follows:
No quota is charged and no action is required from you.
When you
create a
cluster, select the Use reservation consumption
option and then specify your reservation. Cluster Director creates
the cluster from your reserved capacity.
You're charged for the entire reservation period, whether or not you use
the reserved resources for the entire period. For more information, see
Dynamic Workload Scheduler pricing.
Flex-start
For this consumption option, no reservation is required. To get
Flex-start resources, the process is as follows:
When you
create a
cluster, select the Use Flex-start consumption option.
When your requested capacity becomes available, Cluster Director
provisions your cluster. You obtain resources for up to seven days.
You're charged when the resources are in use. Resources provisioned
using Flex-start automatically get discounts through
Dynamic Workload Scheduler pricing.
Spot
For this consumption option, no reservation is required. To get
Spot resources, the process is as follows:
[[["Easy to understand","easyToUnderstand","thumb-up"],["Solved my problem","solvedMyProblem","thumb-up"],["Other","otherUp","thumb-up"]],[["Hard to understand","hardToUnderstand","thumb-down"],["Incorrect information or sample code","incorrectInformationOrSampleCode","thumb-down"],["Missing the information/samples I need","missingTheInformationSamplesINeed","thumb-down"],["Other","otherDown","thumb-down"]],["Last updated 2026-10-06 UTC."],[],[]]