Managed migration is an automated feature that helps you migrate data from a
self-managed Hive Metastore to a Dataproc Metastore service, without
any sizable downtime (otherwise known as a [flag day](https://en.wikipedia.org/wiki/Flag_day_(computing))).

## Managed Migration Architecture

The following diagram provides the high-level architecture of a managed
migration.

![Dataproc Metastore managed migration](https://docs.cloud.google.com/static/dataproc-metastore/images/dpms-managed-migration.png)

### Managed migration flow

To complete a managed migration, your service runs through two migration
processes---[*start migration*](https://docs.cloud.google.com/dataproc-metastore/docs/use-managed-migration#start_migration) and [*complete migration*](https://docs.cloud.google.com/dataproc-metastore/docs/use-managed-migration#complete_migration).
You can cancel a migration at any time with the *cancel migration* process.
There are also a number of operational commands you can run, which aren't
required to complete a migration. For example, [*list migrations*](https://docs.cloud.google.com/dataproc-metastore/docs/use-managed-migration#list_migrations) or [*delete
migrations*](https://docs.cloud.google.com/dataproc-metastore/docs/use-managed-migration#delete_migrations).

As your service moves through this process, it also moves between various
*migration states* and *migration phases* . These states and phases represent the
processes that are occurring in the background. For example, the `MIGRATING`
state indicates that your service is actively transferring data from your
Cloud SQL database to Dataproc Metastore.

**Start Migration**

- **Dataproc Metastore establishes a connection with your
  private IP Cloud SQL instance**. After the connection is made,
  Dataproc Metastore uses the Cloud SQL instance as its
  Hive Metastore (HMS) backend database. It also remains as the source of
  truth for your data during the migration. Metadata reads and writes still
  occur in Cloud SQL when the migration is active.

- **A change data capture (CDC) pipeline is started**. This pipeline keeps the
  Cloud SQL instance in your project and Spanner in the
  Dataproc Metastore managed project in sync. This means that
  all changes to the HMS database in the Cloud SQL instance are captured
  through Datastream and written to the
  Dataproc Metastore Spanner database.

Once the start migration process is successful, you can start routing
data workloads to Dataproc Metastore. At this point, Cloud SQL is
still the source of truth for your data.

**Complete migration**

After you finish moving your workloads to Dataproc Metastore, you
can complete the migration. When a *complete migration* process is called,
the following occurs:

- Dataproc Metastore transitions into a read-only mode until the *complete migration* process finishes.
- The CDC stream transfers all in-flight data to Dataproc Metastore.
- Dataproc Metastore connects to Spanner and disconnects from Cloud SQL. Dataproc Metastore now acts as the source of truth for your HMS data.

## Proxy and pipeline considerations

**Proxies**

Dataproc Metastore uses a [Cloud SQL Auth proxy](https://docs.cloud.google.com/sql/docs/mysql/sql-proxy)
chained to a SOCKS5 proxy to connect to your private IP Cloud SQL instance.
The SOCKS5 proxy servers are exposed through a service attachment as shown
in previous [architecture diagram](https://docs.cloud.google.com/dataproc-metastore/docs/about-managed-migration#how-migration-works).

- Each migration requires a dedicated NAT subnet. This is because
  a NAT subnet can't have more than one service attachment.

- To avoid cross-region latency issues, provide subnets that are in the
  same region as your Cloud SQL instance to host the SOCKS5 proxy. For example,
  `proxy_subnet` and `nat_subnet`.

**Change data capture pipeline**

The change data capture pipeline uses VPC peering to establish a connection
between Datastream and private IP Cloud SQL.

- For each migration, a new private connection is created and a new
  peering connection is established.

- The VPC network hosting the Cloud SQL instance has as many
  peering connections as there are active migrations. Make sure that your
  VPC network has the capacity to host all of the necessary peering connections.