Google Cloud manages your Contact Center AI Platform (CCAI Platform) instances to ensure that they
receive security updates, new features, and performance improvements. You can
control the timing of those updates by choosing a deployment schedule for your
instance.

There are three deployment schedules:

- **Rapid**. Get updates as early as possible. Google recommends the rapid
  deployment schedule for instances that are in pre-production environments,
  such as development or testing instances.

- **Regular**. Get updates at least two days after updates are available with
  rapid deployment. These updates are performed in parallel with critical
  updates.

- **Critical**. Get updates outside of your peak business hours, starting at
  least two days after updates are available with rapid deployment. We update
  instances set for the critical deployment schedule generally within one week
  after all rapid deployment schedule instances are updated, although delays
  beyond one week can occur. We recommend the critical deployment schedule for
  instances that are in production environments.

> [!IMPORTANT]
> **Important:** Google immediately applies security patches to CCAI Platform instances with regular and critical deployment. These are not delayed for two days after rapid deployment.

CCAI Platform instances that were created before deployment schedules
were available are set for rapid deployment.

You can select a deployment schedule when you [create a CCAI Platform
instance](https://docs.cloud.google.com/docs/get-started#create-ccaip-instance). You can also change the
deployment schedule for an existing instance.

Deployment schedules are intended to ensure that upgrades are not done during
peak hours. They are not intended to block upgrades for weeks at a time.
Google Cloud operates its own maintenance freezes during large national events
such as elections, holidays, and peak scale events. If you want to block
upgrades of your instance during your own special event, you can open a
Google Cloud support request to ask us to block upgrades for your instance.

We don't block instance upgrades for more than one release. Because releases
occur approximately every three weeks, this means that we won't block instance
upgrades for more than six weeks.

To check the deployment schedule for an instance, do the following:

1. In the Google Cloud console, go to the project selector dashboard and select the
   Google Cloud project that contains your instance.


   [Project selector dashboard](https://console.cloud.google.com/projectselector2/home/dashboard)

   <br />

2. In the navigation menu, click **CCAI Platform**.


   [CCAI Platform instances](https://console.cloud.google.com/contact-center-ai-platform)

   <br />

   The **CCAI Platform instances** page displays. The deployment
   schedule is in the **Schedule** column for your instance.

To change the deployment schedule for an instance, do the following:

1. In the Google Cloud console, go to the project selector dashboard and select the
   Google Cloud project that contains your instance.


   [Project selector dashboard](https://console.cloud.google.com/projectselector2/home/dashboard)

   <br />

2. In the navigation menu, click **CCAI Platform**.


   [CCAI Platform instances](https://console.cloud.google.com/contact-center-ai-platform)

   <br />

   The **CCAI Platform instances** page displays.
3. For the instance that you want to edit, click **More options** , and then click
   **Edit**.

4. Click **Configure deployments**.

5. In the **Deployment schedule** field, select the deployment schedule that
   you want. If you select **Critical**, you must define your peak business
   hours by creating at least one schedule. To create a schedule, do the
   following:

   1. Click the **Days** field, select the days to include in this schedule,
      and then click **OK**.

   2. In the **Start time** field, enter the start time, including AM or PM.
      Times are in UTC.

   3. In the **End time** field, enter the end time, including AM or PM. Times
      are in UTC.

      A summary of your schedule appears in local time.
   4. Optional: Click
      **Arrow up** or
      **Arrow down** to move schedules up or down.

   5. Optional: Click **Delete** to
      delete a schedule.

   6. If you need additional schedules, click **Add schedule** and repeat
      these steps.

6. Click **Save**.